The activity duration originally assigned to a schedule activity; this duration is typically not updated as progress is reported on the activity. Used for comparison with activity actual duration and activity remaining duration when reporting schedule progress. The activity original duration is normally developed by reliance on historical data, specialists, resource availability, financial considerations, and volume of work to be performed. Also known as planned duration.