Activity Remaining Duration

The total number of work periods, in calendar units, (a) equal to the original duration for an activity that has not started or (b) between the data date of the project schedule and the critical path method (CPM) early finish date of a schedule activity that has an activity actual start date. This represents the time needed to complete a schedule activity where the work is in progress. See also remaining duration.